Polyurea Coating Construction Technology

The construction process of polyurea coating is divided into: substrate processing, polyurea coating spraying, post-treatment, sealant construction, topcoat construction (not required).

Substrate treatment is the key to ensuring construction quality and can be divided into metal substrates and concrete substrates.

Metal substrate treatment, first sandblasting the substrate to Sa2.5 level, for the defect parts such as welds, use epoxy putty to level, so that the entire substrate can smoothly transition, after the epoxy putty is cured, grind with an angle grinder level. Then clean the substrate, roll or brush the two matching primers.

Concrete substrate treatment, shot blasting of concrete precast parts, or use of angle grinders, high pressure water guns, etc. to remove dust and scum from the surface. After the substrate is completely dried, the surface is leveled with a caulking material, and the caulking portion is required to be solidified and then ground with an angle grinder. Then remove the dirt on the surface, brush or roll a matching primer and set it aside.

The primer recoating interval is up to 24 hours and the shortest is 3 hours.

Spraying polyurea coating, spraying of polyurea coating should be carried out within 3 to 168 hours after primer application. If the interval is more than 168 hours, a primer should be re-constructed one day before spraying polyurea coating, and then polyurea is applied. Floor. Dry high pressure air is used to blow off the surface dust before spraying.

Before spraying, you should consider the surrounding environment, use plastic film to cover the surrounding objects that may be contaminated, and protect the surrounding environment.